1 TWZ Series Oil-Fired Hot W ater Boilers INST ALLA TION INSTRUCTIONS These instructions must be affixed on or adjacent to the boiler Models: • TWZ065 • TWZ075 • TWZ100 • TWZ090 • TWZ125 •.
2 T able of Contents I. Product Description ............................................................. 1 II. Specifications ....................................................................... 1 III. Before Installing ...........................
3 TABLE 1a: GENERAL SPECIFICATIONS Notes: 1 . Net Ratings are based on piping and pick-up allowances of 1.15. 2 . Burner Capacity Rating, GPH is based on #2 oil with a Gross Heating Value equal to 140000 BTU/Gal. 3 . Maximum Working Pressure, Water - 50 PSI.
4 3) Make sure that the boiler is correctly sized: • For heating systems employing convection radiation (baseboard or radiators) use an industry accepted sizing method such as the I=B=R Heat Loss Calculation Guide (Pub. #H21 or #H22) published by the Hydronics Institute in Berkeley Heights, NJ.
5 FIGURE 2: CLEARANCES 0. 47" Sh e e t M e t a l ( 2 4 G A o r T hic k e r ) H ol l ow M a s on r y B l oc k s O p e n in g s Alig n e d T o P er m i t F r ee A ir Ci r c ul a ti o n 4“ MI N .
6 V Air for Combustion and V entilation Sufficient fresh air must be supplied for combustion and ventilation. Provisions for combustion and ventilation air for oil burning equipment must be made in accordance with Section 1.5, Air for Combustion and Ventilation, in the latest edition of Installation of Oil Burning Equipment (ANSI/NFPA 31).
7 FIGURE 4: BOILER INSTALLED IN CONFINED SPACE, ALL AIR FROM INSIDE used, they must be no finer than ¼” (4 x 4) mesh. For Buildings of Unusually Tight Construction: 1 ) Openings must be installed between the boiler room and the outdoors or a ventilated space, such as an attic or crawl space, which communicates directly with the outdoors.
8 FIGURE 5: ALL AIR FROM OUTDOORS, VENTILATED CRAWL SPACE AND ATTIC FIGURE 6: ALL AIR FROM OUTDOORS, VIA VENTILATED ATTIC 7.
9 FIGURE 7: ALL AIR FROM OUTDOORS, USING OPENINGS INTO BOILER ROOM FIGURE 8: ALL AIR FROM OUTDOORS, USING HORIZONTAL DUCTS INTO BOILER ROOM 8.
10 FIGURE 9: TYPICAL VENT SYSTEM INSTALLATION AND COMPONENTS VI V enting Vent installation must be in accordance with local building codes, or the local authority having jurisdiction. Typical vent installation is illustrated by Figure 9. The components of vent installation are the vent connector (breeching), barometric draft regulator, and chimney.
11 6 ) Prior to boiler installation, inspect chimney for obstructions or other defects and correct as required. Clean chimney as necessary. 7 ) Vent pipe should slope upward from boiler not less than one inch in four feet. No portion of vent pipe should run downward or have sags.
12 FIGURE 10: STANDARD BOILER PIPING CAUTION • INSTALL BOILER SO THAT ALL ELECTRICAL COMPONENTS ARE PROTECTED FROM WATER (DRIPPING, SPRAYING, RAIN, ETC.
13 2) Circulator (Required) - Figure 10 shows the ideal location of the circulator which is in the supply piping immediately downstream of the expansion tank. A less ideal, but acceptable, location for most residential circulators is in the return (if this is done, be sure that adequate clearance exists to open the door.
14 FIGURE 12: BOILER BYPASS PIPING FIGURE 11: INDIRECT WATER HEATER BOILER SIDE PIPING Piping for Special Situations Certain types of heating systems have additional requirements. Some of the more common variations follow: 1) Indirect Water Heaters - Figure 11 shows typical indirect water heater piping.
15 FIGURE 13: ISOLATION OF BOILER FROM SYSTEM WITH A HEAT EXCHANGER 3) Low Temperature Systems - Some systems, such as radiant tubing systems, require the system water temperature to be limited to a value below the temperature of the water leaving the TWZ.
16 2) Flow Restrictor (Recommended) - If water is drawn from the tankless coil at a rate in excess of the rating in Table 1b, the temperature of the hot water may be too low to be of use. The use of a flow restrictor will prevent this problem by limiting the rate at which water can pass through the tankless heater.
17 FIGURE 14: TANKLESS HEATER PIPING IX Fuel Line Piping Fuel line piping design, materials and construction must be in accordance with local building codes, requirements of the local authority having jurisdiction, and, the latest edition of Installation of Oil-Burning Equipment (ANSI/NFPA 31).
18 FIGURE 16: ONE-PIPE LIFT SYSTEM b) ONE-PIPE LIFT SYSTEM (not recommended) - Used when a fuel oil storage tank is located below an oil burner fuel pump. See Figure 16. The vertical distance from bottom of the tank to center line of the pump (Dimension ‘H’) must not exceed that shown in the pump manufacturer’s instructions.
19 FIGURE 17: TWO-PIPE GRAVITY FEED SYSTEM FIGURE 18: TWO-PIPE LIFT SYSTEM 18.
20 X Wiring WARNING All wiring and grounding must be done in accordance with the authority having jurisdiction or, in the absence of such authority, with the National Electric Code (ANSI/NFPA70). Single Zone Wiring 1) 120 V olt W iring - The boiler should be provided with its own 15A branch circuit with fused disconnect.
21 FIGURE 19: WIRING DIAGRAM, SINGLE HEATING ZONE ONLY FIGURE 20: WIRING DIAGRAM, CIRCULATOR ZONE WIRING USING HONEYWELL R845A’s (FACTORY BOILER WIRING NOT SHOWN - SEE FIGURE 19) 20 L1 I N T ERRUPT .
22 XI S tart-up and Checkout Use the following procedure for initial start-up of the boiler: 1) Ensure that the boiler and entire heating system are filled with water. 2) Check all new piping for leaks and purge heating system piping sections that are air bound.
23 6) Check initial settings of oil burner air band and air shutter, head setting etc., and readjust if needed. See Table 3 for setup and combustion data pertaining to a particular boiler/ burner combination. 7) Attach plastic hose to oil pump vent fitting and provide a container to catch oil during oil pump bleeding procedure.
24 TABLE 3a: BECKETT BURNER CONFIGURATION AND SETUP DATA 23 TABLE 3b: CARLIN BURNER CONFIGURATION AND SETUP DATA TW Z0 6 5 TW Z0 7 5 TW Z1 0 0 TW Z 0 9 0 TW Z1 2 5 TW Z1 5 0 TW Z1 2 0 TW Z1 7 5 TW Z2 0 0 B U R N E R M O D E L E Z - 1 H PE Z - 1 H PE Z - 1 H PE Z - 1 H PE Z - 1 H PE Z - 1 H PE Z - 1 H PE Z - 2 H P S T A NDA R D DE L.
25 XII Service and Maintenance The following procedure should be performed on an annual basis: 1) Turn off electrical power and oil supply to the boiler. 2) Clean the boiler as follows: a) Remove vent connector and piping. b) Remove barometric draft regulator.
26 CAUTION WATER LEAKS CAN CAUSE SEVERE CORROSION DAMAGE TO THE BOILER OR OTHER SYSTEM COMPONENTS. REPAIR ANY LEAKS FOUND IMMEDIATELY. IMPORTANT • CLEAN THE BOILER EVEN IF THERE ARE NO SIGNIFICANT SOOT DEPOSITS. FAILURE TO REMOVE ALL SULFUR AND ASH DEPOSITS ANNUALLY CAN CAUSE SEVERE CORROSION DAMAGE.
27 26 Important Product Safety Information Refractory Ceramic Fiber Product Warning : The Parts list designates parts that contain refractory ceramic fibers (RCF).
28 27 65 75 100 90 125 150 120 175 200 1 COMPLETE HEAT EXCHANGER ASSY. 1 ea. 270013 270013 270013 270014 270014 270014 270015 270015 270015 * FRONT SECTION 275050 1 ea. 1 ea. 1 ea. 1 ea. 1 ea. 1 ea. 1 ea. 1 ea. 1 ea. * REAR SECTION 275060 1 ea. 1 ea. 1 ea.
29 28.
30 29 65 75 100 90 125 150 120 175 200 40 LEFT SIDE JACKET PANEL 1 ea. 270233 270233 270233 270234 270234 270234 270235 270235 270235 41 RIGHT SIDE JACKET PANEL 1 ea. 270223 270223 270223 270224 270224 270224 270225 270225 270225 * REAR JACKET PANEL 270220 1 ea.
31 30.
32 Manufacturer of Hydronic Heating Products P .O. Box 14818 3633 I. Street Philadelphia, P A 19134 7 HO)D[.
Ein wichtiger Punkt beim Kauf des Geräts Crown Boiler TWZ100 (oder sogar vor seinem Kauf) ist das durchlesen seiner Bedienungsanleitung. Dies sollten wir wegen ein paar einfacher Gründe machen:
Wenn Sie Crown Boiler TWZ100 noch nicht gekauft haben, ist jetzt ein guter Moment, um sich mit den grundliegenden Daten des Produkts bekannt zu machen. Schauen Sie zuerst die ersten Seiten der Anleitung durch, die Sie oben finden. Dort finden Sie die wichtigsten technischen Daten für Crown Boiler TWZ100 - auf diese Weise prüfen Sie, ob das Gerät Ihren Wünschen entspricht. Wenn Sie tiefer in die Benutzeranleitung von Crown Boiler TWZ100 reinschauen, lernen Sie alle zugänglichen Produktfunktionen kennen, sowie erhalten Informationen über die Nutzung. Die Informationen, die Sie über Crown Boiler TWZ100 erhalten, werden Ihnen bestimmt bei der Kaufentscheidung helfen.
Wenn Sie aber schon Crown Boiler TWZ100 besitzen, und noch keine Gelegenheit dazu hatten, die Bedienungsanleitung zu lesen, sollten Sie es aufgrund der oben beschriebenen Gründe machen. Sie erfahren dann, ob Sie die zugänglichen Funktionen richtig genutzt haben, aber auch, ob Sie keine Fehler begangen haben, die den Nutzungszeitraum von Crown Boiler TWZ100 verkürzen könnten.
Jedoch ist die eine der wichtigsten Rollen, die eine Bedienungsanleitung für den Nutzer spielt, die Hilfe bei der Lösung von Problemen mit Crown Boiler TWZ100. Sie finden dort fast immer Troubleshooting, also die am häufigsten auftauchenden Störungen und Mängel bei Crown Boiler TWZ100 gemeinsam mit Hinweisen bezüglich der Arten ihrer Lösung. Sogar wenn es Ihnen nicht gelingen sollte das Problem alleine zu bewältigen, die Anleitung zeigt Ihnen die weitere Vorgehensweise – den Kontakt zur Kundenberatung oder dem naheliegenden Service.